Leesburg Street Maintenance Begins Sept. 23

Milling and paving work will smooth over surfaces, eliminate potholes.

The Town of Leesburg will begin conducting pavement improvements along several streets in town starting Sept. 23.

The work is part of the town’s regular street maintenance program, and will include milling and paving, which will eliminate potholes and smooth over the surfaces.

Milling and paving must be done under dry conditions, so rain delays are possible.

The following road segments are scheduled for work next week:

Find out what's happening in Leesburgwith free, real-time updates from Patch.

Chancellor Street (entire street)

  • Milling: Monday, Sept. 23, 7 a.m. to 5:30 p.m.
  • Paving: Tuesday, Sept. 24, 7 a.m. to 5:30 p.m.

Clagett Street, from 500-block cul-de-sac to Periwinkle Way

Find out what's happening in Leesburgwith free, real-time updates from Patch.

  • Milling: Monday, Sept. 23, 7 a.m. to 5:30 p.m.
  • Paving: Tuesday, Sept. 24, 7 a.m. to 5:30 p.m.

Country Club Drive, from South King Street to Governors Drive

  • Milling: Tuesday, Sept. 24, 7 a.m. to 5:30 p.m.
  • Paving: Wednesday, Sept. 25, 7 a.m. to 5:30 p.m.

Greenway Drive, from South King Street to Sheridan Way

  • Milling: Wednesday, Sept. 25, 7 a.m. to 5:30 p.m.
  • Paving: Thursday, Sept. 26, 7 a.m. to 5:30 p.m.